Latest IBM 000-124 Question 3
A POWERS 520 customer is running IBM i 54 and is moving to a POWER7 server. Which of the following is a valid migration plan?
A. MigratelBMi5.4tothePOWER7
B. Host IBM i 54 in a client LPAR on the POWER7
C. Upgrade from IBM i 5.4 to IBM i 7.1 after migrating to POWER7
D. Upgrade to IBM i 7.1 on the Power 520, then migrate to POWER7
Answer: D
A POWERS 520 customer is running IBM i 54 and is moving to a POWER7 server. Which of the following is a valid migration plan?
A. MigratelBMi5.4tothePOWER7
B. Host IBM i 54 in a client LPAR on the POWER7
C. Upgrade from IBM i 5.4 to IBM i 7.1 after migrating to POWER7
D. Upgrade to IBM i 7.1 on the Power 520, then migrate to POWER7
Answer: D